A quick update on the construction progress of our new facility-

 

The ‘not-so-good news’

Weather and contractor personnel issues have put us behind schedule. We are now shooting for Memorial Day weekend opening. It is entirely possible that we open with concrete floors in the bar area since the carpeting for that area is a very long lead item and is produced overseas. Best case scenario is that we open 100% complete, worse case is the carpeting is added two weeks later.

 

The ‘good news’

The construction crew is now running with maximum personnel on site and are quickly making up for lost time.

 

This spring the Club will have a TrackMan radar unit available for the golf Pros to use for coaching. The same unit will be used in a golf simulator in the new facility.

 

http://trackmangolf.com/

 

Our planning committee is evaluating other projects around the Club as well, more talk on that later.

 